AET delivers the APODI cement factory’s electrical assembly


AET recently delivered, in January 2015, the APODI cement factory’s electrical project, which holds the capacity for the daily production of 4 thousand tons of cement.

AET managed and supervised the entire factory’s electrical installation, including:

  • 2km 30MVA in 6,6kv transmission Line
  • 4 substation in 6,6kv electromechanical installation;
  • Factory’s lighting system;
  • Lightning protection system;
  • ELECTRICAL installation and medium and low voltage motors tests

Under AET’s management and supervision, APODI’s construction took 24 months to be completed, with the collaboration of over 190 professionals including engineers, technicians and other fields specialized professionals.